Project Overview
Process Pictures
Pictures After
Scope of Work
Good Life Construction rebuilt a two-story deck and staircase with new ledgers, posts, joists, stringers, handrails and guardrails. Trex composite decking finished the deck surface. Approved changes added framing repairs at a dry rot connection, revised the specified lumber to redwood, and added railing beside the first stair flight.
Challenges
Dry rot at the existing connection required opening the surrounding siding before the framing could be repaired. The rebuilt structure also needed coordinated ledger flashing and railing placement alongside existing windows and exterior openings.
Solutions
Good Life Construction replaced the affected framing, reinstated the siding, and rebuilt the deck and stair assembly using the revised redwood specification. Flashed connections and the additional stair railing completed the work around the existing building.
Final Result
- Deteriorated connection framing replaced and new stair and deck guards installed.
- Rebuilt stairs and Trex decking restored the exterior access route.
- Flashed connections protected the repaired building-to-deck transitions.